Supporting direct labor $6 per direct labor
Machine processing $2 per machine - hour
Machine setups $45 per setup
Production orders $160 per order
Shipments $115 per shipment
Product sustaining $775 per product
Activity data have been supplied for the following two products:
Total Expected Activity
J78 W52
Direct labor hours 1,000 30
Machine hours 2,600 20
Machine setups 19 3
Production orders 19 3
Shipments 38 3
Product sustaining 3 3
Required:
Determine the total overhead cost that would be assigned to each of the products.